Paver Base Calculator

Pavers last as long as what is under them. Enter the size of the paved area and what it will carry, and the calculator gives the base material, the bedding sand and the bags of polymeric sand for the joints, using the thicknesses published by the concrete paver industry.

Enter your paver area

Units

Minimum base thickness from the Concrete Masonry & Hardscapes Association: 4 in after compaction for patios and walkways, 6 in for driveways on well-drained soil.

The CMHA says to screed bedding sand to about 1 in, uncompacted. Enter 0 to leave the sand out.

Coverage of a 50 lb bag of Alliance Gator Maxx G2 for pavers 2⅜ in high.

Planning figure for crushed stone, check with your supplier.

Planning figure for sand, check with your supplier.

The thickness is the finished one, and loose stone takes up more room. Ask your supplier how much to add; 0 gives the finished volume.

Base material

2.37 cubic yards

≈ 3.32 tons · 4 in base under 192 sq ft (17.84 m²)

Paver base estimate
Area192 sq ft (17.84 m²)
UsePatio or walkway
Base thickness4 in
Base material2.37 yd³ (64 cu ft)
Base weight at 1.4 tons per yd³3.32 tons
Bedding sand thickness1 in
Bedding sand0.593 yd³ (16 cu ft)
Sand weight at 1.3 tons per yd³0.77 tons
Extra for compaction and waste0%
Polymeric sand, narrow, ⅛ to ⅜ in joints3 bags of 50 lb (65 to 85 sq ft per bag)

Formula: area × thickness for the base and for the bedding sand, plus the extra; weight = cubic yards × density. Base thicknesses: CMHA Tech Note PAV-TEC-002-22 (4 in after compaction for patios and walkways, 6 in thick for residential driveways on well-drained soils; bedding sand about 1 in, uncompacted). Densities are planning figures, check with your supplier. Polymeric sand: coverage per 50 lb bag of Alliance Gator Maxx G2 in Beige, Slate Grey or Ivory, for pavers 2⅜ in high; other products and colors differ.

How thick the base and sand should be

The Concrete Masonry & Hardscapes Association (CMHA) gives the thicknesses in Tech Note PAV-TEC-002-22, Construction of Interlocking Concrete Pavements. Sidewalks, patios and pedestrian areas should have a base at least 4 inches thick after compaction. Residential driveways on well-drained soils should be at least 6 inches thick. The bedding sand on top is spread and screeded to a nominal 1 inch, uncompacted.

Base and bedding thickness (CMHA Tech Note PAV-TEC-002-22, well-drained soil)
UseBase thicknessBedding sand
Sidewalks, patios, foot traffic4 inches minimum, after compactionAbout 1 inch, screeded
Residential driveways6 inches minimumAbout 1 inch, screeded

These are minimums. Poorly drained soil and cold climates often call for more, and the menu has a choice for your own base thickness when the plans or your paver supplier give one.

The paver base formula

Base volume = area × base thickness × (1 + extra ÷ 100)
Sand volume = area × sand thickness × (1 + extra ÷ 100)
Tons = cubic yards × density
Polymeric sand bags = area ÷ coverage per bag, rounded up

The calculator converts the thickness from inches to feet, so 4 inches is one third of a foot. Cubic feet divide by 27 to give cubic yards. The weight uses 1.4 tons per cubic yard for the base and 1.3 for the sand. These are planning figures: for sand, Caltrans lists 1.2 to 1.3 tons per cubic yard. Check with your supplier and enter their figures in the density boxes.

The CMHA gives the 4-inch patio minimum as a thickness after compaction, and the calculator treats every base thickness as the finished one. Loose stone from the truck takes up more room than it does after the plate compactor has passed, so the extra box is there for compaction and waste. It starts at 0, which gives the finished volume. Ask your supplier how much to add for the material you buy. The gravel calculator starts its extra box at 5 percent instead.

Worked example: a 12-by-16-foot patio

A patio of 12 by 16 feet covers 192 square feet. It carries foot traffic, so the base is 4 inches, with 1 inch of bedding sand and narrow joints.

  • Base: 192 × 4 ÷ 12 = 64 cubic feet, or 2.37 cubic yards
  • Base weight: 2.37 × 1.4 = 3.32 tons
  • Bedding sand: 192 × 1 ÷ 12 = 16 cubic feet, or 0.593 cubic yards, about 0.77 tons
  • Polymeric sand: 192 ÷ 85 = 2.26 and 192 ÷ 65 = 2.95, so 3 bags of 50 lb

With 10 percent extra, a planning figure to check with your supplier, the base becomes 2.607 cubic yards and the bedding sand 0.652 cubic yards, because the box adds the same percentage to both. An 8-inch base under the same patio doubles the stone to 4.741 cubic yards. A 20-by-24-foot driveway with a 6-inch base needs 8.889 cubic yards of base, about 12.44 tons, and with wide joints 12 to 22 bags of polymeric sand.

Polymeric sand for the joints

Polymeric sand is swept into the joints after the pavers are laid and compacted, then wetted so it hardens. How far a bag goes depends on the joint width and the size and shape of the pavers. The calculator uses the coverage that Alliance Gator publishes for its Gator Maxx G2 sand in Beige, Slate Grey and Ivory, for pavers 2⅜ inches high, in its reference guide. The Black Diamond color covers a little less, and other brands publish their own figures, so check the bag you buy.

Polymeric sand coverage per 50 lb bag (Alliance Gator Maxx G2, pavers 2⅜ inches high)
Joint widthCoverage per bagBags for 100 sq ftBags for 500 sq ft
⅛ to ⅜ in (narrow)65 to 85 sq ft2 to 26 to 8
¾ to 1¼ in (wide)22 to 42 sq ft3 to 512 to 23

Because coverage is a range, the result is a range too. Alliance Gator says the amount needed depends on the shape and size of the pavers and on the width of the joints.

Measuring and what is left out

Measure the paved area itself. If the base runs out past the edge restraint, add that strip to the length and width. For an L-shaped patio, add the parts with the square footage calculator. The count of the pavers themselves is on the paver calculator, and loose sand or gravel sold by the yard is on the sand and gravel calculators. Geotextile, edge restraints and excavation are not counted.

Paver Base Calculator FAQ

How much paver base do I need for a 12-by-14 patio?

With a 4-inch base, 56 cubic feet, which is 2.074 cubic yards or about 2.9 tons, before any extra.

How thick should the base be under a paver driveway?

The CMHA says residential driveways on well-drained soils should be at least 6 inches thick, and that colder climates and wet or weak soils need a thicker base.

Should bedding sand be compacted before the pavers go down?

No. The CMHA says to spread and screed it to a nominal 1 inch, uncompacted. Enter that thickness in the bedding sand box: for 192 square feet it gives 16 cubic feet.

How many bags of polymeric sand do I need?

For narrow joints of ⅛ to ⅜ inch, a 50 lb bag of Gator Maxx G2 covers 65 to 85 square feet of pavers 2⅜ inches high. For wide joints of ¾ to 1¼ inches, it covers 22 to 42.

Is the base thickness measured before or after compaction?

The CMHA gives the 4-inch minimum for patios and walkways as a thickness after compaction. The calculator treats the thickness as the finished one, so order a little more loose stone. Your supplier can say how much.